How to respond to plan check corrections

Your permit came back with a correction letter. Here's how contractors and owner-builders answer it in one round: what the letter means, how to revise the plans, how to write the response, and what to send back.

Updated October 23, 2026 · General information, not legal or engineering advice. Requirements vary by jurisdiction.

What a plan check correction letter is

When you apply for a building permit, a plans examiner reviews your drawings against the building, electrical, plumbing, mechanical, energy and zoning codes your city or county has adopted. Anything missing, unclear or not code-compliant comes back as a correction letter. Depending on where you are it may be called a correction list, plan review comments, a plan check letter or simply "redlines."

A typical letter has numbered items, each with a short comment, and often the code section and the sheet it applies to. Some reviewers also mark up the plans themselves with clouds and notes. Your job is to answer every item, change the plans where needed, and send everything back so the reviewer can approve it.

Step 1: Read the whole letter and sort the comments

Read every item before you change anything. Then sort them into a few piles:

Sorting first shows you what's on your critical path. If you need an engineer, contact them on day one, since that is usually the slowest part.

Step 2: Look up the code behind each comment

Most comments cite a code section, such as IRC R314 for smoke alarms or NEC 690.12 for PV rapid shutdown. Read that section in the edition your jurisdiction actually adopted, and check for local amendments. Cities and counties often adopt the model codes with their own changes, and many publish them on their building department website.

Understanding why the reviewer asked usually tells you exactly what to draw. A comment like "show compliance with R310" means the reviewer wants to see emergency escape opening sizes and sill heights for the sleeping rooms.

Step 3: Revise the plans and cloud every change

Make each change on the drawings, then identify it so the reviewer can find it quickly:

  1. Draw a revision cloud around each change.
  2. Add a delta tag (a small triangle with the revision number) next to the cloud.
  3. Add a line to the revision block in the title block with the revision number, date and a short description, such as "Plan check corrections, round 1."

Only cloud what changed in this round. Leaving old clouds on the sheets makes the reviewer re-check work that was already approved.

Step 4: Write the response letter

The response letter answers each comment in order, using the reviewer's numbering. For every item, restate the comment, explain what you did, and say where it is on the plans. A table works well:

#CommentResponseLocation
1Show smoke and CO alarms in the existing dwelling per CRC R314 and R315.Added hardwired, interconnected smoke alarms in each bedroom and hallway, and a CO alarm outside the sleeping area.Sheet A-1, notes 6 and 7
2Provide distance from new patio cover to the rear property line.Dimensioned 12'-6" from the patio cover post to the rear property line. Exceeds the 5'-0" setback.Sheet SP-1
3Provide manufacturer's installation instructions for the solar collectors.Attached the manufacturer's installation manual and SRCC certification.Attachment B

Keep responses specific and factual. "See revised plans" or "Will comply" forces the reviewer to hunt for your change, and that's how a second round of comments starts.

Got a correction letter right now?Upload it and get every item explained in plain English, a drafted response, clouded plans and a checklist. Free during early access.

Answer my corrections

Step 5: Resubmit the complete package

Before you upload or drop off the resubmittal, check that it includes everything the department asks for. Usually that's:

Watch the clock as well. Under the model building codes, an application can be treated as abandoned if it isn't pursued for 180 days (IBC and IRC section 105.3.2), and many departments set their own deadlines for responding to corrections.

Tips for getting approved on the next review

Frequently asked questions

How long does a plan check recheck take?

It varies widely by jurisdiction and workload. Rechecks are often faster than the first review because the reviewer only looks at the corrected items, but some departments put resubmittals back in the same queue. Check your department's posted review times or ask the reviewer.

Why do reviewers reject "Will comply" as a response?

"Will comply" doesn't show the reviewer that anything changed on the plans. Reviewers approve what is drawn, so each response should say what was changed and where to find it, for example "Added smoke alarm in bedroom 2, see sheet A-1, note 7."

Do I have to cloud my revisions?

Most building departments ask you to identify every change on the resubmitted sheets, usually with a revision cloud and a delta tag that matches the revision number in the title block. Check your department's resubmittal instructions, since some also want a written list of changed sheets.

What if I disagree with a correction?

Answer it anyway. Explain your position politely in the response, cite the code section and edition that supports it, and offer to talk it through. Calling or emailing the reviewer before you resubmit often settles it faster than a second round of comments.

Can I resubmit only the sheets that changed?

Some departments accept only the revised sheets, while others want a complete updated set. Electronic plan review portals usually spell this out. When in doubt, ask, because a resubmittal in the wrong format can be returned without review.

Common plan check corrections and how to fix themThe comments reviewers write most often, by permit type, and what to change on your plans.Free site plan maker for building permitsDraw a scaled, permit-ready site plan in your browser and export a print-ready PDF.Answer my correctionsUpload a correction letter and get drafted responses, clouded plans and a checklist.