Revision clouds and deltas for permit resubmittals

Reviewers approve what they can see changed. Revision clouds and delta tags are how you show them. Here's how to draw and number them, and the rule that differs most between departments: whether last round's clouds stay on the sheets.

Updated October 24, 2026 · By the Plan Check Correct team · General information, not legal or engineering advice. Requirements vary by jurisdiction.

What clouds, deltas and the revision block are

Together they let a reviewer flip through a resubmitted set, find every change, and tie it to a submittal date, without comparing the old and new sheets line by line.

How to cloud a resubmittal

  1. Cloud every change, including small ones like a new note or a corrected dimension. Draw the cloud tightly around the change, not around the whole sheet.
  2. Put a delta next to each cloud with this submittal's revision number.
  3. Add a line to the revision block on every sheet that changed: the delta number, the date, and a description such as "Plan check corrections, round 1."
  4. Number revisions in order. The first resubmittal is usually 1, the next one 2, and so on.
  5. Point to the clouds in your response letter. For each comment, give the sheet and detail where the reviewer will find the clouded change. Our response letter template has room for this.
Some departments put this in writing. The City of Malibu's delta revision worksheet asks for every revised area to be clouded, a delta number next to each cloud, the revision noted with its date in the title block, and sequential delta numbers, and says resubmittals that don't clearly identify their revisions will be rejected.

Old clouds: remove them or keep them?

This is the part that varies most. The City of Milpitas shows both approaches in one handout, depending on what you're submitting:

What you're resubmittingWhat Milpitas asks for
A new permit application that's still in plan checkCloud this round's changes with a delta for this resubmittal, and turn off the clouds from earlier submittals. Resubmit the complete drawing set.
A revision to a permit that's already issuedKeep all clouds and deltas from the first revision submittal and every resubmittal on the drawings, and cloud new changes with the revision's own delta number. Only clouded, numbered changes count as part of the approved revision.

Other departments have their own rules, and many don't write them down. If yours doesn't say, ask the reviewer or the permit counter before you resubmit. A common approach is to keep the full history in the revision block while clouding only the current round's changes on the drawings.

Got a correction letter right now?Upload it and get every item explained in plain English, a drafted response, clouded plans and a checklist. Free during early access.

Answer my corrections

Changes the reviewer didn't ask for

If you change something that wasn't in the correction letter, cloud it like any other change and call it out separately. Milpitas, for example, asks for a separate letter describing changes that aren't part of the responses to comments, with the sheet numbers. Unannounced changes can trigger new comments, or simply be missed and left out of what was approved.

Drawing clouds on a PDF

CAD programs have a revision cloud command, and PDF editors such as Adobe Acrobat and Bluebeam include cloud markup tools. Plan Check Correct also draws them for you: load your plan PDF, drag a box where each change is, and it adds the revision cloud, delta tag and note for that correction. Before uploading to an electronic plan review portal, check its instructions. Some ask for markups to be flattened into the PDF, or for one file per sheet named a certain way.

Mistakes that send a resubmittal back

Frequently asked questions

What does the delta symbol mean on plans?

A delta is a small triangle with a number in it. The number is the revision the change belongs to, and it matches a line in the revision block of the title block that gives the date and a short description. A delta 1 next to a cloud means that change was made in revision 1.

Should I remove revision clouds from the previous submittal?

It depends on the department and the kind of submittal. For a permit still in plan check, many departments want only the current round's changes clouded and earlier clouds turned off. For a revision to a permit that's already issued, some want every cloud and delta from the revision kept on the drawings. Check your department's resubmittal instructions, and ask if they don't say.

Do I need to cloud changes the reviewer didn't ask for?

Yes. Cloud every change, and list the ones that weren't in response to a comment separately in your letter. Unmarked changes can be missed in review, and some departments only treat clouded, numbered changes as part of the approved revision.

Can I resubmit without clouds?

Usually not. Many departments return a resubmittal that doesn't identify its changes. The City of Malibu, for example, says it will reject a resubmittal that doesn't clearly cloud the revised areas and number them with deltas.

Sources

How to respond to plan check correctionsA step-by-step guide to answering a correction letter and getting approved on the next review.How to write a plan check response letterA fill-in template and sample responses a reviewer can check off quickly.Building permit rejected? What to do nextAn incomplete application, plan check corrections or a real denial: how to tell, and what to do about each.Common plan check corrections and how to fix themThe comments reviewers write most often, by permit type, and what to change on your plans.Solar permit plan check correctionsComments on PV, battery storage and solar pool heating permits, and what to change on the plans.Answer my correctionsUpload a correction letter and get drafted responses, clouded plans and a checklist.